Jan 7, 2026
BOM & Change Management
Engineering Change Order Process: Complete Implementation Guide

An Engineering Change Order (ECO) is the formal process for modifying a product after its initial release. When implemented correctly, ECOs take 2-3 days from request to implementation. When implemented poorly, they take 3-4 weeks, introduce errors, and frustrate everyone involved.
This guide explains how to design and optimize an engineering change order process that balances speed with control, reduces approval time by 60-80%, and eliminates the manual errors that plague most change management systems.
Who this guide is for:
PLM program managers implementing or optimizing change processes
Engineering managers frustrated with slow change approval cycles
Quality leaders ensuring traceability and compliance
Manufacturing planners dealing with frequent design changes
IT directors configuring PLM workflow systems
What you'll learn:
The difference between ECO, ECN, ECR, and when to use each
How to design approval workflows that are fast but controlled
Change categorization by risk (not all changes are equal)
Integration between PLM, ERP, and manufacturing systems
How to eliminate the bottlenecks that slow down most ECO processes
Metrics to track change management effectiveness
Reading time: 24 minutes
Complexity level: Intermediate
Prerequisites: Basic PLM knowledge helpful but not required
What Is an Engineering Change Order (ECO)?
The Simple Definition
An Engineering Change Order (ECO) is a document that describes, approves, and authorizes changes to a product, component, or process after it has been formally released.
Key components:
What's changing (parts, BOMs, specifications, documents)
Why it's changing (problem being solved, improvement being made)
Who approved it (signatures/approvals from required stakeholders)
When it takes effect (effectivity date, serial number cutover)
How it impacts (cost, schedule, inventory, customers)
ECO vs ECN vs ECR: What's the Difference?
These three terms are often confused. Here's the distinction:
ECR - Engineering Change Request
Purpose: Propose a change (request for approval)
Status: Not yet approved
Who creates: Anyone (engineer, quality, customer, supplier)
Typical workflow: Request → Review → Approve/Reject
If approved: Becomes an ECO or ECN
ECO - Engineering Change Order
Purpose: Authorize and implement a change
Status: Approved
Who creates: Engineering (usually from approved ECR)
Typical workflow: Create → Approve → Implement → Close
Scope: Can include BOMs, drawings, specifications, processes
ECN - Engineering Change Notice
Purpose: Notify others of an approved change
Status: For information only (change already approved)
Who creates: Engineering
Typical workflow: Create → Distribute → Acknowledge
Scope: Usually informational (not requiring implementation actions)
In practice: Many organizations use ECO and ECN interchangeably. What matters is having a clear, consistent process—not the specific terminology.
Element's recommendation: Use ECR for requests, ECO for approved changes. Skip ECN unless you need a separate notification step.
Why Most ECO Processes Are Too Slow
The Typical Timeline Problem
Scenario: Engineer needs to change a part material from aluminum to steel (simple change).
Typical ECO timeline:
Day | Activity | Status |
|---|---|---|
1 | Engineer creates ECO in PLM | Waiting for review |
2-3 | Engineering manager reviews | Approved to quality |
4-6 | Quality reviews (manager on vacation) | Waiting |
7-8 | Manufacturing reviews | Questions material availability |
9-10 | Purchasing confirms material | Approved to operations |
11-13 | Operations reviews | Approved to finance |
14-16 | Finance reviews cost impact | Questions pricing |
17-18 | Back to engineering for clarification | Clarified |
19-20 | Final approvals | Approved to implementation |
21 | Manufacturing planner implements | Finally done |
Total time: 21 days for a simple material change.
Cost of delay:
Engineering team delayed waiting for approval (wasted productivity)
Manufacturing using old material (potential quality issue)
Customer delivery delayed (competitive disadvantage)
Opportunity cost (what else could team have worked on?)
The Five Bottlenecks
Bottleneck #1: Serial Approvals (Everyone Waits)
The problem: Each approver waits for the previous person to approve before seeing the change.
Why it's slow: If quality manager is on vacation (days 4-6), everyone downstream waits even though the change doesn't affect them.
The fix: Parallel approvals. Everyone who needs to review sees it simultaneously.
Time saved: 17 days → 4 days (76% reduction)
Bottleneck #2: All Changes Treated Equally
The problem: Simple documentation update requires same approval as safety-critical change.
Examples:
Fixing typo in drawing title → 7 approvals, 2 weeks
Changing material that affects strength → 7 approvals, 2 weeks
Updating supplier on BOM → 7 approvals, 2 weeks
Why it's slow: Approvers spend time on low-risk changes that don't need their expertise.
The fix: Categorize changes by risk. Route based on impact.
Low risk (1 approval, same-day):
Documentation corrections
Drawing clarifications
Title/description updates
Non-functional changes
Medium risk (3 approvals, 2-3 days):
Material changes (non-critical)
Supplier changes
Process improvements
Cost reduction initiatives
High risk (full approval, 5-7 days):
Safety-critical changes
Regulatory impact
Customer-visible changes
Major cost increase (>$10K)
Time saved: 67% of changes are low-risk → processed in 1 day instead of 14 days.
Bottleneck #3: Unclear Change Description
The problem: Approvers can't tell what changed, so they ask questions or delay approval.
Bad ECO description:
"Update Part 12345"
What approvers see: Part number. No context. They have to:
Open part in PLM
Compare current version to previous
Try to figure out what changed
Ask engineer for clarification
Wait for response
Time wasted: 2-3 days per approver.
Good ECO description:
Change: Part 12345-A material from Aluminum 6061 to Stainless Steel 304
Reason: Corrosion observed in field after 6 months (RMA-847)
Impact: +$8.40 per unit cost, no fit/function change, same suppliers
Effectivity: Serial numbers 1001 and higher
Affected Products: Model X (227 units in inventory), Model Y (none in stock)
What approvers see: Complete picture. Can approve immediately if they agree with rationale.
Time saved: Eliminates clarification loops (2-3 days per approver).
Bottleneck #4: Approvers Don't Check PLM Daily
The problem: ECO sits in queue for days because approver doesn't know it's there.
Typical scenario:
Engineer submits ECO Monday morning
Quality manager gets email notification
Quality manager doesn't check PLM until Thursday (busy with other work)
Thursday: Quality approves
ECO sat idle for 3 days
Why it's slow: Approvers are reactive (respond when they remember to check) not proactive (notified effectively).
The fix: Better notifications + escalation
Notification improvements:
Email subject: "ACTION REQUIRED: ECO-2847 Material Change (High Priority)"
Email body: Complete change description (don't make them open PLM)
Direct link: "Approve" button in email (one-click)
Visual: Before/after comparison image
Escalation rules:
24 hours: Reminder email
48 hours: Email to approver's manager
72 hours: Auto-approve (if low-risk) or escalate to director (if high-risk)
Time saved: Reduces approval time from 3-7 days to <24 hours.
Bottleneck #5: Implementation Happens Manually
The problem: After ECO approval, someone manually updates ERP, MES, quality systems.
Manual implementation steps:
Export BOM from PLM (CSV file)
Open ERP
Find manufacturing BOM
Manually update 47 line items
Make 2 typos (catch 1, miss 1)
Update work instructions in MES
Update inspection criteria in quality system
Hope everything matches
Time wasted: 2-4 hours per ECO
Error rate: 8-12% (something gets updated wrong)
The fix: Integration between PLM, ERP, MES, quality systems
Automated implementation:
ECO approved in PLM → Trigger integration
Integration reads BOM changes
Validates data
Updates ERP manufacturing BOM
Updates MES work instructions
Updates quality inspection plans
Notifies affected people
Logs completion
Time saved: 2-4 hours → 3 minutes (98% reduction)
Error rate: 12% → 0.3% (96% reduction)
The Element ECO Framework: 4-Phase Approach
Phase 1: Process Design (Week 1-2)
Goal: Design an ECO process that balances speed with appropriate control.
Step 1: Define Change Categories
Not all changes are equal. Categorize by risk to route appropriately.
Low Risk:
Documentation corrections (typos, clarifications)
Non-functional changes (color, cosmetic)
Supplier updates (approved alternative)
Minor cost reductions (<$500)
Medium Risk:
Material changes (non-critical parts)
Process improvements
Dimensional changes (non-critical)
Cost changes ($500-$10K)
High Risk:
Safety-critical changes
Regulatory impact (FDA, FAA, etc.)
Customer-visible changes
Major cost increase (>$10K)
Form/fit/function changes
Deliverable: Change categorization matrix with examples.
Step 2: Design Approval Workflows
For each category, define:
Who must approve (required)
Who should review (optional/FYI)
Approval sequence (serial vs parallel)
Timeframe expectations
Escalation rules
Example workflows:
Low Risk (Fast Track):
Medium Risk (Standard):
High Risk (Full Approval):
Deliverable: Workflow diagrams for each change category.
Step 3: Define Effectivity Rules
Effectivity determines when a change takes effect. Options include:
Immediate:
Takes effect as soon as approved
Use for: Documentation corrections, non-impactful changes
Risk: May affect work in process
Date-based:
Takes effect on specific date
Use for: Planned improvements, supplier transitions
Requires: Coordination with planning
Serial number:
Takes effect at specific unit number
Use for: Mid-production changes, phased transitions
Requires: Traceability system
Lot-based:
Takes effect at specific lot/batch
Use for: Material changes, process changes
Requires: Lot tracking in ERP/MES
Deliverable: Effectivity policy document.
Phase 2: System Configuration (Week 3-4)
Goal: Configure PLM system to support designed process.
Step 1: Create Change Object Types
In PLM, define:
ECR (Engineering Change Request):
Fields: Problem description, proposed solution, impact analysis
Workflow: Request → Review → Approve/Reject
If approved: Creates ECO
ECO (Engineering Change Order):
Fields: What's changing, why, impact, effectivity
Workflow: Based on change category (low/medium/high risk)
Links to: Parts, BOMs, documents affected
MCO (Manufacturing Change Order) - Optional:
Same as ECO but originates from manufacturing
Use when: Manufacturing-driven process improvements
Step 2: Configure Workflows
For each workflow:
Define states:
Draft (being created)
In Review (circulating for approval)
Approved (ready to implement)
In Work (implementation in progress)
Complete (implemented and verified)
Cancelled (if withdrawn)
Define transitions:
What triggers each state change
Who can make each transition
What validations must pass
Define notifications:
Who gets notified at each state
What information is included
When reminders are sent
How escalation works
Step 3: Create Templates
Standard templates ensure consistency:
ECO Description Template:
Deliverable: PLM system configured with workflows and templates.
Phase 3: Integration (Week 5-8)
Goal: Connect PLM to downstream systems so approved changes flow automatically.
Step 1: PLM → ERP Integration
What to sync:
Part master changes (description, attributes, etc.)
BOM changes (new parts, revised quantities, obsolete parts)
Revision updates (part at Rev B instead of Rev A)
Effectivity dates
When to sync:
When ECO state = "Approved"
Real-time (event-driven) vs batch (nightly)
Element recommendation: Real-time for critical changes, batch for minor updates
What to validate:
Part numbers match naming convention
BOM structure valid (no circular references)
Required fields populated
No duplicate records
What to log:
Every sync transaction (success or failure)
What data was sent
What errors occurred
Who to notify if failed
Step 2: PLM → MES Integration
What to sync:
Work instruction updates (reflect design changes)
BOM changes (build to correct revision)
Routing updates (if process changed)
Quality checkpoints (updated inspection criteria)
Complexity:
MES must reflect current approved design
Can't have operators building to old work instructions
Must handle in-process work (what about units mid-build when change happens?)
Effectivity handling:
If serial-based: Update work instructions to show both versions (before/after)
If date-based: Schedule cutover for clean break (between shifts)
Step 3: PLM → Quality System Integration
What to sync:
Inspection plan updates (what to inspect)
Acceptance criteria updates (pass/fail limits)
Test procedure updates (how to test)
Calibration requirements (if measurement changed)
Critical: Quality must inspect to correct revision. Building Rev C but inspecting to Rev A criteria = defects missed.
Phase 4: Rollout & Adoption (Week 9-12)
Goal: Train users, deploy process, achieve 80%+ adoption.
Week 9: Change Champion Training
Identify champions (one per department):
Engineering: Senior engineer who "gets it"
Quality: QA manager with process focus
Manufacturing: Lead planner
Operations: Ops manager
Train them deeply:
How the process works (not just how to use it)
Why it's designed this way (business rationale)
How to handle edge cases
How to train their teams
Why champions matter:
Peers trust peers more than management
They speak department language
They're there after consultants leave
Week 10: Pilot Launch
Start with one product family:
20-30 active parts
5-7 users
Mix of change types (low/medium/high risk)
2-week pilot
Monitor closely:
Daily standup with pilot users
Track every ECO (timeline, issues)
Fix problems within 24 hours
Build confidence through responsiveness
Success criteria:
95%+ ECOs approved within target timeline
Zero critical errors
User satisfaction >4/5
Week 11: Phased Rollout
Expand incrementally:
Week 11: Add 3 more product families
Week 12: Add remaining products
Why phased:
Catch issues at small scale
Build confidence gradually
Don't overwhelm support team
Support structure:
Daily office hours (Week 11)
Weekly office hours (Week 12+)
On-demand help (always)
Week 12: Optimization
Review first 100 ECOs:
Average approval time by category
Where did delays occur?
What caused confusion?
What needs adjustment?
Common refinements:
Adjust risk categories (some items miscategorized)
Simplify notifications (too much information overwhelming)
Add automation (eliminate remaining manual steps)
Update training (address common mistakes)
Deliverable: Optimized, self-sufficient ECO process.
Common ECO Process Mistakes
Mistake #1: No Change Categorization
The problem: Every change goes through full approval process regardless of risk.
Example consequences:
Engineer fixes typo in drawing title → 7 approvals, 2 weeks
Approvers get approval fatigue (too many trivial changes)
When critical change comes through, it's not recognized as urgent
Organization becomes slow to respond
The fix: Categorize by risk. Fast-track low-risk changes. Focus attention on high-risk changes.
Mistake #2: Serial Approvals for Parallel Work
The problem: Approvers wait for each other when they could review simultaneously.
Example: Quality waits for engineering manager approval before seeing change. But quality's review is independent—they don't need to see manager's input first.
Time wasted: 2-3 days per serial step × 5 steps = 10-15 days.
The fix: Parallel approvals whenever possible. Serial only when dependent (e.g., cost approval must wait for cost calculation).
Mistake #3: Weak ECO Descriptions
The problem: Approvers can't tell what changed or why it matters.
Bad example:
"Update Part 12345"
Result: Approvers must:
Open part record
Compare versions
Guess what changed
Ask originator for clarification
Wait for response
Time wasted: 1-2 days per approver.
The fix: Require complete description using template (what, why, impact, effectivity).
Mistake #4: No Escalation for Delayed Approvals
The problem: ECO sits in someone's queue for days/weeks because they forgot or are busy.
Example:
Engineer submits ECO Monday
Sits with quality manager (vacation, then busy)
Noticed Thursday (3 days later)
Quickly approved (takes 5 minutes)
Time wasted: 3 days (72 hours) for a 5-minute review.
The fix: Escalation rules:
24 hours: Reminder
48 hours: Manager notification
72 hours: Auto-approve (low-risk) or escalate to director (high-risk)
Mistake #5: Manual Implementation After Approval
The problem: Approval happens in PLM, but implementation is manual in downstream systems.
Result:
2-4 hours per ECO for manual data entry
8-12% error rate
Trust erosion (PLM says Rev C, ERP says Rev B)
The fix: Integration between PLM and downstream systems. Approved change triggers automatic updates.
Metrics to Track ECO Process Health
Primary Metrics
1. Cycle Time by Change Category
Category | Target | Measured | Status |
|---|---|---|---|
Low Risk | <8 hours | 4.2 hours | ✅ Healthy |
Medium Risk | <3 days | 2.1 days | ✅ Healthy |
High Risk | <7 days | 8.3 days | ⚠️ Slightly over |
How to measure: Timestamp from "submitted" to "approved" state.
What good looks like: 90%+ of ECOs meet target for their category.
2. Approval Bottleneck Analysis
Track time spent in each approval stage:
Approver | Average Days | % Over 3 Days |
|---|---|---|
Engineering Manager | 0.8 | 5% |
Quality | 1.2 | 12% |
Manufacturing | 3.4 | 47% |
Operations | 0.9 | 8% |
Finance | 2.1 | 23% |
What this reveals: Manufacturing is the bottleneck (3.4 days, 47% over target).
Action: Investigate why. Common causes:
Understaffed (too many changes, not enough reviewers)
Unclear responsibilities (who should approve what?)
Poor ECO descriptions (need clarification)
Low priority (other work takes precedence)
3. Implementation Accuracy
Measure: % of ECOs implemented correctly first time (no errors).
How to track:
Post-implementation audit (spot-check 10% of ECOs)
Error reports (discrepancies found by users)
Rework required (had to fix implementation)
Target: >95% accuracy
What good looks like:
98%+ for integrated systems (automated implementation)
85-92% for manual implementation (human error inevitable)
4. Effectivity Compliance
Measure: % of changes that took effect on intended date/serial number.
How to track:
Compare intended effectivity to actual implementation date
Check if inventory properly segregated (pre-change vs post-change units)
Verify manufacturing built to correct revision
Target: 100% for critical changes, 95%+ overall
What bad looks like:
Manufacturing built 50 units to old revision after change approved
Inventory mixed (can't tell which units have change)
Customer shipped product with wrong revision
Supporting Metrics
5. Change Volume Trends
Track: Number of ECOs per month by category.
Why it matters:
Increasing low-risk changes: Maybe categorization too permissive
Increasing high-risk changes: Product stability issues? Quality problems?
Decreasing changes: Product maturing (good) or stagnation (bad)?
6. Change Reasons
Categorize: Why changes are happening.
Common categories:
Corrective (fix defect/problem)
Enhancement (improve product)
Cost reduction
Regulatory/compliance
Obsolescence (supplier discontinuation)
Why it matters:
High % of corrective: Quality issues in design process
High % of cost reduction: Good (continuous improvement)
High % of obsolescence: Supplier management problems
7. Customer Impact
Measure: % of changes that require customer notification.
Why it matters:
Form/fit/function changes affect customers
Too many: Product stability issues, customer frustration
Document and manage carefully
Target: <10% of changes require customer notification
ECO Process for Regulated Industries
Additional Requirements for FDA, FAA, ISO
Regulated industries (medical devices, aerospace, etc.) have stricter requirements:
1. Complete Traceability
Must be able to trace which units have which changes
Serial number or lot traceability required
Audit trail of all approvals and implementations
2. Change Review Board
Formal board meets regularly (weekly/monthly)
Reviews all changes above certain threshold
Minutes documented
Quorum requirements
3. Impact Assessment
Risk analysis required for each change
Failure modes and effects analysis (FMEA)
Verification and validation testing
Documentation of rationale
4. Change Notification
Customers notified of form/fit/function changes
Regulatory bodies notified (if required)
Certificates updated (if specifications changed)
Formal notification process
5. Configuration Control
Strict control of effectivity
No mixed configurations in inventory
Clear delineation of pre/post-change units
Traceability to end customer
FDA Specific (Medical Devices)
FDA requires:
Design History File (DHF):
All changes documented
Rationale for changes
Verification/validation evidence
Approval signatures
Change Control SOPs:
Documented procedures
Who can approve what
When to file 510(k) supplement
When to notify FDA
30-Day Notice:
Certain changes require 30-day FDA notification before implementation
Labeling changes, major design changes
PMA Supplement:
Major changes require Pre-Market Approval supplement
180-day FDA review
Cannot implement until approved
FAA Specific (Aerospace)
FAA requires:
Configuration Management Plan:
How changes are controlled
Effectivity tracking
Supplier change management
Type Certificate Data Sheet Updates:
Changes to certificated aircraft require TCDS update
Engineering authorization required
Flight testing may be required
Airworthiness Directives:
Safety-critical changes may trigger AD
Mandatory implementation
Fleet-wide notification
Templates & Checklists
ECO Description Template
ECO Review Checklist
For Approvers - Use This to Review ECOs:
☐ Change Description Clear
Can I tell exactly what's changing?
Do I understand why it's changing?
Is the problem/opportunity clearly stated?
☐ Impact Fully Analyzed
Cost impact assessed?
Schedule impact assessed?
Inventory impact assessed?
Customer impact assessed?
☐ Effectivity Defined
When does this take effect?
Is cutover plan clear?
What happens to in-process units?
☐ Implementation Plan Complete
Who does what?
When does each step happen?
Are dependencies identified?
☐ Risk Assessment Adequate
What could go wrong?
How is risk mitigated?
Is testing plan sufficient?
☐ My Department Ready
Do we have required materials/resources?
Is training needed?
Are procedures updated?
☐ Customer Notification
Does customer need to know?
Is notification plan in place?
Is approval required?
If all checked, APPROVE. If any concerns, REQUEST CLARIFICATION.
Getting Started: Your 30-Day ECO Process Improvement
Week 1: Current State Assessment
Day 1-2: Data Collection
Pull last 50 ECOs from PLM
Measure cycle time (submission to approval)
Identify bottlenecks (where did they sit longest?)
Track approval sequence (serial or parallel?)
Day 3-4: User Interviews
Interview 5 people who create ECOs (engineers, quality)
Interview 5 people who approve ECOs (managers, directors)
Ask: "What frustrates you about the ECO process?"
Day 5: Analysis
Calculate average cycle time by change type
Identify top 3 bottlenecks
Determine % of ECOs that are truly high-risk (probably <20%)
Deliverable: One-page current state summary.
Typical findings:
Average cycle time: 14-21 days (too long)
67% of changes are low-risk (could be fast-tracked)
Serial approvals adding 10-15 days
No escalation (ECOs sit idle)
Week 2: Process Redesign
Day 6-7: Change Categorization
Define low/medium/high risk categories
Classify last 50 ECOs into categories
Validate categories with stakeholders
Day 8-9: Workflow Design
Design fast-track workflow for low-risk
Design standard workflow for medium-risk
Design full approval for high-risk
Switch serial to parallel where possible
Day 10: Notification Design
Improve email notifications (include full context)
Add escalation rules (reminder, manager notification, auto-approve)
Add direct approval links (one-click approve)
Deliverable: New ECO process design document.
Week 3: System Configuration
Day 11-13: PLM Configuration
Create change categories in PLM
Configure workflows (low/medium/high)
Set up notifications and escalations
Create ECO description template
Day 14-15: Testing
Test each workflow in dev/test environment
Verify notifications working
Confirm escalations triggering correctly
Get user feedback on templates
Deliverable: Configured PLM system ready for pilot.
Week 4: Pilot & Optimization
Day 16-18: Pilot Launch
Select 10 users for pilot
Process 15-20 ECOs through new workflows
Monitor closely (daily check-ins)
Fix issues immediately
Day 19-20: Analysis
Review pilot results
Measure cycle time improvement
Collect user feedback
Identify refinements needed
Deliverable: Validated process ready for full deployment.
Expected results:
Cycle time reduced 60-80%
User satisfaction improved
Approval bottlenecks eliminated
When to Get Help
DIY vs Professional Services
You can likely handle internally if:
Simple workflows (one approval path)
Small user base (<20 people)
No integration required (PLM only)
Time available (not urgent)
Consider professional help if:
Complex workflows (multiple approval paths, many approvers)
Regulated industry (FDA, FAA, ISO requirements)
Integration needed (PLM, ERP, MES, quality systems)
Timeline is aggressive (need results in 60-90 days)
High change volume (>100 ECOs/month)
What Element Consulting Provides
ECO Process Design:
Current state assessment
Workflow design (categorization, approvals, routing)
Template creation
Metrics definition
System Implementation:
PLM configuration
Integration design and build
Testing and validation
User training
Change Management:
Champion training
Pilot management
Rollout support
Adoption tracking
Deliverables:
Documented ECO process
Configured PLM system
Integration to downstream systems (if needed)
Trained users
60-80% cycle time reduction (typical)
Conclusion: Fast ECO Process = Competitive Advantage
Engineering agility matters. Companies that can change products quickly respond faster to:
Customer requests
Quality issues
Competitive threats
Supplier changes
Regulatory requirements
Most ECO processes optimize for control at the expense of speed. You can have both—appropriate control with 3-day cycle times instead of 3-week cycle times.
The key is differentiation:
Not all changes are equal (categorize by risk)
Not all approvers are needed for every change (route intelligently)
Not all steps need to be serial (parallelize when possible)
Not all implementation needs to be manual (integrate systems)
Element's framework gets you there:
Categorization by risk
Parallel approvals
Clear descriptions
Escalation rules
Automated implementation
Result: 60-80% faster ECO process without sacrificing control.
Your Next Step
Free ECO Process Assessment:
Answer 15 questions about your current ECO process.
Get:
Cycle time estimate
Bottleneck identification
Improvement opportunity score
Benchmark vs industry
Time: 8 minutes
Cost: Free
Take ECO Assessment →
30-Minute Expert Review:
Quick call with Element ECO process specialist.
We'll review:
Your current cycle time
Your biggest bottlenecks
Quick wins (fast improvements)
Long-term optimization approach
Time: 30 minutes
Cost: Free, no obligation
Schedule Review →
Related Resources
Knowledge Base:
ERP-PLM Integration Guide - Automate ECO implementation across systems
Bill of Materials Management - How ECOs affect BOMs
Change Management for PLM - Getting users to adopt new ECO process
Blog Posts:
Case Studies:
About Element Consulting
Element Consulting specializes in optimizing PLM processes, including engineering change management, for manufacturing companies.
Our approach:
Process first, technology second
Appropriate control without sacrificing speed
Integration across systems (PLM, ERP, MES, quality)
Knowledge transfer (you become self-sufficient)
Industries we serve:
Aerospace & Defense (AS9100 compliance)
Automotive (IATF 16949 compliance)
Medical Devices (FDA compliance)
Industrial Equipment
Our experience:
127 ECO process optimizations
Average 68% cycle time reduction
Zero compliance failures
92% user adoption
Contact us:
eco@elementconsulting.com
Schedule a call →
Last updated: January 2026
Version: 1.8
Reading time: 24 minutes
Word count: 8,934

